Tucson Unified School District

CONSTRUCTION


Project Statistics


Year Completed: 2014

Project Name: Tucson Unified School District Fiber Ring

Owner: Zayo Group

Contract: Hard Bid

Industry: Broadband

Department: Construction


Project Description


Our team was awarded the contract by the Zayo Group to design, permit and construct 10.3 miles of new underground construction and 27.2 miles of aerial installation to connect over 65+ schools in the Tucson Unified School District via a dark fiber network. The project was surveyed, engineered, permitted and constructed by BPG Designs. The project was constructed using directional bore and backhoe activities. 95% of this project was constructed by using horizontal directional drill rigs. To meet the tight construction deadline by our client, BPG successfully utilized and managed several sub contractors to meet the project objectives and goals. BPG was also responsible for all final restoration and permit close out documentation.